Network Working Group Elmer B. Shapiro
Request for Comment: 4 Stanford Research Institute
Category: Informational 24 March 1969
Network Timetable
1 (n10) network checkout
2 Installation of communcation gear 8/1/69
2a From AT&T and/or BBN need dimensional, power and cabling
specifications
2b Need to establish SRI desired alternate locations so as to
determine maximum telco cable lengths
2c Need to establish location and drops on voice coordination
circuits
2d Need circuit information on voice drops for tie to intercom
system
2e Need to order and install a.c. power (coordinate with 4b)
2f See 16
3 Design and construct host-Imp interface 9/1/69
3a Need specifications from BBN
3b Develop trial design
3c Review with system programmers
3d Establish final design
3e Build and design hardware
3f Debug trial software with hardware loop test
4 Imp installation 9/15/69
4a from BBN get dimensional, power and cabling specifications
4b SRI orders and installs a.c. power (coordinate with 2e)
5 Debug host-Imp interface 10/1/69
5a Get debug specifiations and procedures from BBN
5b Write programs to debug with BBN
5b1 Transfers of test messages
5b2 Test procedures for crash and recovery
5b3 Check message fill and stripping procedures
5c Try own transfer tests
5c1 Verify transfers to Imp
5c2 Verify transfers from Imp
5c3 Verify transfers looped with Imp
5d Work out Imp reload and restart procedures
6 Test messages between UCLA-SRI 10/15/69
6a Network configuration
SRI |
|
|
|
|
|
|
|
UCLA |
6b Agree with UCLA on nature of test messages
6b1 Formats
=1= |